Question
Chinu takes 20 days more and
Diksha takes 6 days more than the number of days taken by both of them working together to complete a piece of work. How many days does Chinu take to complete the same piece of work working alone?Solution
ATQ,
Let x be the number of days taken by both Chinu and Diksha working together. Chinu takes 20 days more than both working together = C= x+20. Diksha takes 6 days more than both working together = D=x+6. The combined work rate equation is
Solve for x
Cross-multiply and simplify to get x2 = 120, so x ≈ 11. Chinu takes C = x+20 = 11+20 = 31 days.
Which of the following statement is true?
As per the Companies Act, 2013 a Company means_____________
The registered office clause of memorandum of association contains
When you evaluate a company's financial ratios in relation to other companies in the same industry, what type of comparison is this?
A contract is entered into under duress where one party threatened the other with loss of business if the agreement wasn't signed. The other party signs...
A Red Herring Prospectus does not the include information related to __________
ABC Pvt. Ltd. entered into a contract with Mr. Rao for supplying machinery worth ₹25 lakhs. After execution of the contract, Mr. Rao became insolvent ...
What is the minimum number of members required to form a public company?
A Public Company is a company which has a minimum paid-up share capital ____________
Mr. X, a minor, enters into a contract to buy a bike. Later, he refuses to pay. What is the legal position?