Question
Chinu takes 20 days more and
Diksha takes 6 days more than the number of days taken by both of them working together to complete a piece of work. How many days does Chinu take to complete the same piece of work working alone?Solution
ATQ,
Let x be the number of days taken by both Chinu and Diksha working together. Chinu takes 20 days more than both working together = C= x+20. Diksha takes 6 days more than both working together = D=x+6. The combined work rate equation is
Solve for x
Cross-multiply and simplify to get x2 = 120, so x ≈ 11. Chinu takes C = x+20 = 11+20 = 31 days.
In the question, assuming the given statements to be true, find which of the conclusion (s) among given three conclusions is /are definitely true and t...
Three of the following four letter-clusters are alike in a certain way and one is different. Pick the odd one out.
Select the option in which the numbers are related in the same way as are the numbers of the following sets.
(52, 13, 8)
(96, 16, 12) �...
One day, Anamika leaves her office and walks 30m towards east. She then turned right and walks 30m, and then she again turned right and walks 15m. From ...
If a meaningful four-letter English word is formed by using the 2nd, 5th, 6th and 10th letter (from the left end) of the word ‘COMPONENTS’ then whic...
Which of the following numbers will replace the question mark (?) in the given series?
102, 100, ?, 96, 112
Select the option that is related to the fifth number in the same way as the second number is related to the first number and the fourth number is relat...
Select the correct mirror image of the given figure when the mirror is placed to the right side of the f igure at ‘XY ’.
Which of the following numbers will replace the question mark (?) in the given series?
53, 62, 57, ?, 61, 70, 65
Who is spouse of Z?