πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!

  • google app store apple app store
  • βœ–

      Question

      A and B together can complete a piece of work in 10

      days. A alone can complete the work in 15 days. How many days will B take to complete the work alone?
      A 30 days Correct Answer Incorrect Answer
      B 20 days Correct Answer Incorrect Answer
      C 25 days Correct Answer Incorrect Answer
      D 40 days Correct Answer Incorrect Answer

      Solution

      Let the total work be 1 unit. A’s efficiency = 1/15 (work per day). A and B together = 1/10 (work per day). B's efficiency = (1/10) - (1/15) = (3 - 2)/30 = 1/30 (work per day). Thus, B alone can complete the work in 30 days.

      Practice Next
      ask-question