Question
The ratio of efficiencies of Ajay and Bijay is 7:8, respectively. Ajay and Bijay together can complete the total work in 24 days. In how many days will Bijay alone complete the whole work?
Solution
ATQ, Let the efficiency of Ajay and Bijay be 7 units per day and 8 units per day, respectively. Total amount of work = (7 + 8) Γ 24 = 360 units Time taken by Bijay alone to compete the whole work = 360 / 8 = 45 days
More Time and work Questions
- βAβ alone can complete a work in 10 days. βBβ alone can complete the same work in 20 days. If βAβ and βBβ work together for 3 days, then the remaining work...
- (x + 9) laborers complete 45% of a task in 12 days working 5 hours/day. The rest is done by (x + 4) laborers in 18 days working 5 hours/day. Find x.
- 3 men and 1 boy together can complete a work in 20 days. 2 men and 3 boys can together complete half of the same work in 10 days. Find the time taken by 1 ...
- A alone can complete a piece of work in 12 days and B alone can complete it in 18 days. If they work together, in how many days will they complete the work...
- X men can complete the piece of work in 35 days and (X + 34) men can complete the same work in 14 days less than that of days taken by X men. Find the valu...
- 7 men and 4 boys can complete a work in 6 days. A man completes double the work than a boy. In how many days will 5 men and 4 boys complete the work?
- A and B alone can complete a work in 15 and 30 days, respectively. 50% of the work is completed by C in 2x days, and the remaining work is completed by A a...
- βCβ and βDβ can together complete a piece of work in 20 days. If βCβ alone can do it in 50 days, find the number of days βDβ will take to complete it alone...
- 12 men working for 6 hours a day can complete a work in 20 days. If 30 women are employed to work, then find how many hours a day they have to work to comp...
- John does ½ piece of work in 3 hours, Joe does ¼ of the remaining work in 1 hour and George finishes remaining work in 5 hours. How lon...