      A and B can do a piece of work in 16 days and 18 days

      respectively. A started the work alone and after 4 days B also joined and continued till the work was completed. For how many days did B do the work?
      A 6 days Correct Answer Incorrect Answer
      B 6.35 days Correct Answer Incorrect Answer
      C 6.92 days Correct Answer Incorrect Answer
      D 6.57 days Correct Answer Incorrect Answer

      Solution

      Let the work be completed in x days. According to the question- X/16+x-4/18 =1 18x+16x-64 = 16×18 34x=352 X=352/34 =10.35 Work of B = x-4 =10.35-4 =6.35 days