Question
Armaan and Bhanu jointly received Rs. 9,000 for
completing a task, with Bhanu's share being Rs. 3,000. If Bhanu can complete the work on his own in 48 days, determine the time it takes for Armaan alone to complete the same task.Solution
ATQ, Ratio of efficiency of Aman:Bhanu = (9000 – 3000):3000 = 2:1 So, ratio of the time taken by ‘Aman’ alone to complete the task and ‘Bhanu’ alone to complete the same work, respectively = 1:2 Therefore, time taken by ‘Aman’ alone to complete the work = 48/2 = 24 days
Which industries are part of the Eight Core Industries index?
Which primary objective of the Pradhan Mantri Ayushman Bharat Yojana aims to alleviate the financial burden of healthcare on low-income households?
Which organization acts as the Pension Fund Manager for PM-SYM?
What is the corpus of the AgriSURE fund?
In India, the official measurement of unemployment through the Periodic Labour Force Survey (PLFS) uses which key concept for its annual estimates?
Which of the following ministries is associated with “Aazadi se Antoday take'' campaign?
Under Pradhan Mantri Ujjwala Yojna (PMUY), the beneficiaries get how much subsidy in their bank account and how many subsidized cylinders per year?
Government of India has come up with several initiatives for preventing discrimination against women at the workplace as well as increasing participatio...
Which of the following statements accurately describes the primary vision of the Digital India Mission?
What is the objective of PM krishi sinchayee Yojana, which was launched in 2015-16.
(i)Â Â Â Â Â Â To achieve convergence of investments in i...