Question
Armaan and Bhanu jointly received Rs. 9,000 for
completing a task, with Bhanu's share being Rs. 3,000. If Bhanu can complete the work on his own in 48 days, determine the time it takes for Armaan alone to complete the same task.Solution
ATQ, Ratio of efficiency of Aman:Bhanu = (9000 – 3000):3000 = 2:1 So, ratio of the time taken by ‘Aman’ alone to complete the task and ‘Bhanu’ alone to complete the same work, respectively = 1:2 Therefore, time taken by ‘Aman’ alone to complete the work = 48/2 = 24 days
H2PO4- is absorbed greatest at ph of
Mostly plants absorb micronutrients in
Hypothesis of no difference between the sample mean and population parameter be called as
The spread of numerical value from the mean value is called?
The collection of experimental methods of growing large number of isolated cells under sterile condition?
Sugarcane is a heavy feeder crop but higher doses of nitrogen during ripening stage, ____ the sucrose content in maturing cane.
The United Nations General Assembly (UNGA) has declared 2023 as the International Year of Millets (IYM). The leading country in millet production is
In symbiotic relationship between plant and bacteria
Excellent source of nitrogen in groundnut is
The family to which Citrus spp. belongs is