Question
Saurabh can complete a piece of work in 20 days. He
worked for 5 days and left. Anirudh completed the remaining work in 12 days. If both of them had done the work together, the work would have been completed in how many days?Solution
Saurabh can complete a piece of work in 20 days=1 Saurabh can complete a piece of work in 1 days=1/20 After 5 days =5/20=¼ remaining work=1-¼=¾ ATQ- Anirudh ¾ =12days Anirudh can do a work =16 days so now Saurabh       Anirudh 20                16          80 4                  5 Saurabh and Anirudh had done work complete=80/5+4 =80/9 = 889days Â
Which bank has launched UPI integration for NRE clients through its mobile banking platform enabling NRIs to seamlessly utilise UPI features through the...
Which Indian regulatory body launched the NPS Vatsalya scheme for minors in September 2024?
What is the planned release timeframe for the updated Consumer Price Index (CPI) series?
What is the official name of the High Seas Treaty signed under UNCLOS?
Consider the following statements:
I. QS World University Rankings is an annual publication of university rankings by Quacquarelli Symonds (QS)...
Which agency is organising the anti-terror conference in Delhi where details of India’s first anti-terror policy will be shared?
India recently reached an agreement with China to end a military standoff in which region?
Which company became the first coal company in India to operate four AMRIT pharmacies?
Mount St. Helens is an 'active stratovolcano' located in
Which of the following is not in the six organisations that have been de-recognised by the ESMA?