Question
Saurabh can complete a piece of work in 20 days. He
worked for 5 days and left. Anirudh completed the remaining work in 12 days. If both of them had done the work together, the work would have been completed in how many days?Solution
Saurabh can complete a piece of work in 20 days=1 Saurabh can complete a piece of work in 1 days=1/20 After 5 days =5/20=¼ remaining work=1-¼=¾ ATQ- Anirudh ¾ =12days Anirudh can do a work =16 days so now Saurabh Anirudh 20 16 80 4 5 Saurabh and Anirudh had done work complete=80/5+4 =80/9 = 889days
India’s first greenfield grain based ethanol production plant inaugurated in ………………….
India’s first vaccine to prevent Lumpy Disease was developed by which of the following Institute?
Out of 121 countries, India’s GHI ranking fell from ……………… in 2021 to 107 this year.
World Animal Day is observed on 4th October every year. The theme for World animal day 2022 was:
Green Revolution in India was primarily associated with crops?
The One District One Product (ODOP) programme cover products of agriculture and allied sectors for 728 districts of the country is covered under which s...
FCI coordinates its functions through a country-wide network of offices with Headquarter in…………….
On 24 April_____, the Constitutional (73rd Amendment) Act 1992 came into force to provide constitutional status to the Panchayati Raj institutions.
e- NAM was launched on ………… under the Ministry of Agriculture and Farmer’s welfare.
What is the chemical formula for Salicylic acid?