      Aaru Swati and Rajni can finish a work in 4 days if they

      work together. However, Aaru alone will take 9 days to complete the work, and Swati alone will complete the work in 12 days. How many days will Rajni take alone to complete the work?
      A 25days Correct Answer Incorrect Answer
      B 20days Correct Answer Incorrect Answer
      C 42days Correct Answer Incorrect Answer
      D 16days Correct Answer Incorrect Answer

      Solution

      Aaru =A,Swati=S,Rajni =R Efficiency of R=Efficiency of (A+S+R)-(A+S) =9-7=2 Rajni takes time =36/2= 18days.