Question

Aaru Swati and Rajni can finish a work in 4 days if they work together. However, Aaru alone will take 9 days to complete the work, and Swati alone will complete the work in 12 days. How many days will Rajni take alone to complete the work?

A 25days
B 20days
C 42days
D 16days