Question
Aaru Swati and Rajni can finish a work in 4 days if they work together. However, Aaru alone will take 9 days to complete the work, and Swati alone will complete the work in 12 days. How many days will Rajni take alone to complete the work?
More Time and work Questions
- Gagan can do a piece of work in 14 days. Magan is 40% more efficient than Gagan. How many days will Magan and Gagan together complete the work?
- Person A can complete a work in 90 minutes while Person B takes 54 minutes to complete the same work. How much time will both take together to complete the...
- A, B and C can do a piece of work in 5, 8 and 10 days respectively. They start working together but C leaves after working 1 days and B, 2 days before the ...
- Worker P alone can complete a work in 40 days. If workers P and Q together take 25% less time than P alone to complete the same work, then in how many days...
- 30 typists working 7 hours per day can complete a typing job in 15 days. ____ typists working _____ hours per day can complete (2/3)rd part of the work in ...
- Anita started working and left after 3 days and aftere that Binita started the rest work and finished it in another 5 days. Had Anita left the work after w...
- ‘Z’ alone can complete a project in 48 days, while ‘Z’ and ‘Y’ together can finish it in 16 days. If ‘Y’ worked alone for ‘x’ days and then ‘Z’ completed t...
- A can complete 5/6 of a work in 15 days and B can complete 2/3 of work in 8 days. In how many days both A and B together can complete the work?
- Amit and BK working together can finish a particular task in 90 days, while BK and Chiku working together can complete the same task in 70 days. Determine ...
- ‘A’ and ‘B’ together can complete a work in 8 days, while ‘B’ and ‘C’ together can complete the work in 10 days. If ‘B’ takes 5 days to complete the work a...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)
Efficiency of R=Efficiency of (A+S+R)-(A+S) =9-7=2 Rajni takes time =36/2= 18days.