Question
Numan does 4/ 5 half the work as Gagan in time. If together they take 16 days to complete a piece of work, then how long will Gagan take to complete the work?
More Time and work Questions
- A can fabricate a divider in 20 days , while B alone can assemble it in 30 days, If they construct it together and get an installment of Rs 6000, then find...
- A takes 24 hours more than B to complete the work, and 32 hours more than C to complete the same work. The combined time taken by A and B to finish the wor...
- P’s 3 days work is equal to Q’s 5 days work. If P and Q together can complete the work in 24 days then how much time Q will take to complete 75% of the wor...
- A work can be completed by ‘A’ and ‘B’, alone in 14 days and 7 days, respectively. Find the number of days taken by ‘C’ to complete the same work alone if ...
- 33 men can complete 3/5 part of a work in 8 days working 9 hours a day. How many women can complete rest of the work if they work for 6 hours a day for 33 ...
- How can we determine the value of x, given that (x+8) workers, working 9 hours a day, can finish 60% of a task in 12 days, and (x+2) workers, working 3 hou...
- P and Q can do a piece of work in 20 days and 12 respectively, P started the work alone and then after 4 days Q joined him till the completion of the work....
- ‘X’ can complete a job in 30 days. ‘Y’ is 50% more efficient than ‘X’. How long will they take to finish 75% of the work together?
- The time taken by ‘A’ to build a wall alone is 45% more than the time taken by him to build it along with ‘B’. ‘B’ will take how much percent more time to ...
- ‘A’ and ‘B’ can complete a certain work in 12 days and 24 days, respectively. They started working together and worked till completion of the work for whic...