Question
Ram and Shyam can complete a project in 15 days and 10
days, respectively. They started doing the work together, but after 2 days, Shayam had to leave, and Ram alone completed the remaining work. In how many days was the whole work completed? type-sscSolution
Ram              Shyam 15                        10               30          total works 2                           3            -Efficiency ATQ- 2(Ram +Shyam) + x (Ram)=30 2(2+3) +x (2) =30 2x =30-10=20 X=10days Total days =10+2 =12days
In 2024, the government launched an internship portal as part of The Prime Minister’s Internship Scheme to bridge skill gaps among unemployable youth....
What is the primary objective of the PM Mudra Yojana?
Which of the following information is/are TRUE with respect to the changes made by the Reserve Bank of India in relation to the Small Finance Banks ?
The RBI notified that District Central Co-operative Banks are allowed to close their unremunerative branches without prior permission of the central ban...
The Reserve Bank of India has approved _______ of surplus transfer to the government for 2022-23 and has maintained the contingency risk buffer 50 basis...
Recently which of the following stock exchange has received approval from the Securities Exchange Board of India (SEBI) to set up a social stock exchang...
The fourth LEADS (Logistics Ease Across Different States) 2022 report unveiled by the ministry of ________.
How much financing did the World Bank approve to help India accelerate low carbon energy development in its second round?
India’s Purchasing Managers’ Index (PMI) for manufacturing recovered slightly in October to 55.3 from 55.1 in September,2022 , this survey is compil...
The PMAY-G includes provisions for convergence with other government schemes. Which of the following schemes is NOT typically linked or converged with P...