Question
Ram and Shyam can complete a project in 15 days and 10
days, respectively. They started doing the work together, but after 2 days, Shayam had to leave, and Ram alone completed the remaining work. In how many days was the whole work completed? type-sscSolution
Ram              Shyam 15                        10               30          total works 2                           3            -Efficiency ATQ- 2(Ram +Shyam) + x (Ram)=30 2(2+3) +x (2) =30 2x =30-10=20 X=10days Total days =10+2 =12days
- ‘P’ and ‘Q’ together can finish a task in 15 days while ‘Q’ alone can do it in 25 days. If the ratio of efficiencies of ‘P’ and ‘R’ is ...
If 12 men can build a wall in 15 days, how many men are required to build the same wall in 10 days?
16 men can complete a work in 10 days. 10 men started the same work and left after working for ‘y’ days. The remaining work is completed by 6 men in...
"Akash and Bittu can individually complete a task in 40 days and 50 days, respectively. They start working together, and after 10...
Manoj can complete a job in 10 days which Rakesh can do in 15 days. Rakesh can finish a task in 20 days which Suresh can complete in 25 days. In how man...
- If Rina can complete a project in 36 days by working 9 hours a day, how many hours per day should she work to complete the project in 18 days?
‘A’ and ‘B’ can complete a certain work in 16 days and 32 days, respectively. They started working together and worked till completion of the wo...
- Pipe ‘X’ can fill a tank 15 minutes faster than Pipe ‘Y’. If both are opened together, they can fill the tank in 18 minutes. If 180 litres of water...
3 workers paint 5 rooms in 8 days. How many workers are needed to paint 10 rooms in 6 days?
28 men can complete a work in 20 days. 40 women can complete the same work in 28 days. 20 men and 12 women started working and after 16 days, 20 more wo...