Question
The ratio of time taken by P, Q and R to complete work alone is 6:7:3 respectively. If all three together complete the work in 7 days, then find in how many days P alone will complete two-third of the same work?
More Time and work Questions
- A can complete a piece of work in 27 days. He worked for 21 days and then B finished the remaining work in 8 days. In how many days can A and B finish the ...
- 'Andy' and 'Ben' together can finish some work in 27 days. If 'Andy' alone can finish it in 45 days, then find the time taken by 'Ben' to finish the work a...
- P is 60% more efficient than Q. P takes 30 more days to finish a work as compared to the number of days taken by P and Q together to finish the same work. ...
- A, B and C can complete a work as follows, (A + B) in 12 days, (B + C) in 15 days, and (A + C) in 20 days. In how many days can A alone complete the work?
- Average speed of ‘A’ during a 22-hour journey is 22 km/h. If he covered the first 280 km of his journey at a speed of 20 km/h, then find the speed at which...
- ‘P’ and ‘Q’ can complete a task together in 24 days. If ‘P’ alone can do it in 40 days, find the number of days ‘Q’ alone will take to finish the task.
- P and Q can complete a work in 20 days and 30 days, respectively. P, Q and R together can complete the work in 10 days. If R get a total wage of Rs. 4800 t...
- A and B together can finish a job in 12 days. B alone takes 30 days. How long will A and C together take to finish the same job if C does one-fourth of A’s...
- A, B, and C together can do a work alone in 14 days, 56 days, and 70 days respectively. A alone starts the work and work for 3 days and leaves the work, th...
- A can complete a work in 12 days and B can complete the same work in 18 days. They work together for 4 days, after which A leaves. In how many more days wi...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)