Question
An elephant can do a work as fast as two horses ‘A’ and ‘B’ can do it by working together. If horse ‘A’ alone can complete the work in 27 hours and horse ‘B’ in 54 hours, then find the time taken by elephant to complete the work.
More Time and work Questions
- Working together, Amit and Pawan can finish a task in 22.5 days, and Pawan and Chirag can complete 60% of the same task in 14.4 days. Given that Amit is 12...
- Before 'A' joined the team, 'S' and 'V' were alternating days to complete a project. In the final four days, 'A', 'S', and 'V' all worked together to finis...
- 'A' alone can do some work in 20 days. 'B' is 60% more efficient than 'A'. 'A' worked alone for 12 days and left. How much time (in days) does 'B' need to ...
- A and B together can complete a job in 2 days. A alone takes x + 6 days to complete the job, while B alone takes x + 24 days to complete the same job. 1.W...
- ‘A’ can complete a work in 18 days and is 10% more efficient than ‘B’. ‘A’ and ‘B’ start the work together, but ‘A’ leaves after 15 days. The remaining wor...
- 40 women working 10 hours a day take 12 days to complete a project. How many women working for 7 hours a day are needed to complete twice the given project...
- 40 tailors can stitch a batch of dresses in 30 days. If 20 tailors started the job and after 15 days ‘u’ more tailors joined them such that the remaining w...
- A and B can do a job in 20 days and 30 days, respectively. A and B work together for 5 days, and then A leaves. After how many more days will B complete th...
- Pipe ‘X’ can fill a tank 15 minutes faster than Pipe ‘Y’. If both are opened together, they can fill the tank in 18 minutes. If 180 litres of water passes ...
- Vijay can do a piece of work in 16 days and Sanjay can do the same work in 24 days. If Vijay works for 6 days and got Rs. 2700, and the remaining work will...