Question

A and B individually can complete the work in 16 days and 24 days respectively. If the time taken by C alone to complete the work is 1.25 times the time taken by A and B together to complete the work, find the time taken by C to complete the work while working alone.

MT
A 21 days
B 27 days
C 15 days
D 24 days
E 12 days