Two men A and B started a job in which A was thrice as good as B and therefore took 60 days less than B to finish the job. How many days will they take ...
108 unit of work can be completed by P alone in 18 days. P started working alone and joined by Q after 9 days such that they completed the remaining wor...
If one child has half the work efficiency of an adult, determine the duration required for 8 children to construct a wall, which is 60% as large as the ...
An inlet pipe can fill a tank in 15 minutes when there’s no leakage. However, due to a leak in the tank, it takes 21 minutes to fill it completely. Ho...
‘A’ and ‘B’ can complete a certain work in 16 days and 32 days, respectively. They started working together and worked till completion of the wo...
Krishna can do a piece of work in 25 days. He alone worked at it for 10 days and then Balram completed alone the rest work in 20 days. In how many days,...
A can complete `1/4` of a work in 6 days and B can complete `2/5` of the work in 12 days. In how many days can both A and B together complete the work?<...
A work is done by A, B, C and D together. The percentage of work done by A, B C and D are in arithmetic progression (AP). The first, second, third and f...
X men can complete the piece of work in 36 days and (X + 30) men can complete the same work in 15 days less than that of days taken by X men. Find the v...