Six persons S, T, U, V, W and X have different weights
in kg. T is heavier than U but lighter than S, who is the second heaviest among all. W is lighter than X, who is not the heaviest. Who among the following is the heaviest?Solution
V > S > ? > ? > ? > ? Clearly, V is the heaviest.
- The efficiency ratio of Neha, Karan, and Ishaan is 16:11:14, respectively. Together, they can complete a task in 30 days. Neha and Karan started the task, ...
Two workers A and B were put to some work. If A worked alone, he would have taken 8 hours more than when both A and B had worked together. If B worked a...
P and Q can do a work in 10 days. Q and R can do it in 12 days. All three together can finish in 8 days. In how many days can P and R can complete the w...
A and B can complete a work together in 30 days. If A alone can complete one-third of the work in βxβ days and remaining work is completed by B alon...
A and B individually can complete the work in 20 days and 30 days respectively. If the time taken by C alone to complete the work is 1.25 times the time...
A group of 16 women can complete a certain job in 48 days, working 7 hours each day. How many women would be required to complete the same job in 32 day...
35 men can complete a piece of work in 40 days. βxβ men started the work and after 30 days 60 more men joined them so that whole work was finished i...
Virat can do a piece of work in 28 days and Sachin can do the same work in 42 days. If Virat works for 4 days and got Rs. 1800, and the remaining work w...
The time taken by βAβ to build a wall alone is 50% more than the time taken by him to build it along with βBβ. βBβ will take how much percen...
X men can complete the piece of work in 36 days and (X + 30) men can complete the same work in 15 days less than that of days taken by X men. Find the v...