Question
How many persons are starting the business between B
and M? Study the following information carefully and answer the below questions. Eight persons- A, B, C, D, M, N, O and P are starting their business on different month- March, April, August and November on different dates either 06 or 17 of the month of the year 2020. All the information is not necessarily in the same order. O has started on April 17. Only one person is starting the business between M and N. P has started two persons before D. M has started the business on even numbered date after O. The number of persons starting between B and C is same as between N and D. A has started the business on either November or April. D has started on an odd numbered date. C does not start on even numbered date.Solution
O has started on April 17. M has started the business on even numbered date after O. Only one person is starting the business between M and N. From the above condition, there are three possibilities.
P has started two persons before D. D has started on an odd numbered date.
C does not start on an even numbered date. A is starting the business on either November or April.
The number of persons starting between B and C is same as between N and D. From the above condition, case1 and case3 get eliminated.
Case2 shows the final arrangement.
Â
Ravi and Rekha, alone can complete a work in 25 days and 50 days, respectively. They started the work together and left after 10 days such that the rema...
A alone can finish a piece of work in 10 days and B alone can finish it in 15 days. They work together for 3 days and the remaining work is finished by ...
P, Q & R can finish a work in 10 days, 15 days, and 20 days, respectively, working alone. P and Q work on the first day, P and R work on the second day,...
(x + 6) workers complete 40% of a job in 8 days by working 5 hours/day. The remaining work is done by (x + 2) workers in 16 days working 5 hours/day. Fi...
Amin, Basha and Cheez can do a piece of work in 90, 40 and 12 days respectively. But they decide. That a single person will work in a day and receive Rs...
138 unit of work can be completed by P alone in 23 days. P started working alone and joined by Q after 11 days such that they completed the remaining wo...
- Two workers, A and B, can finish a task in 36 days and 48 days respectively, working alone. How many days will they take to complete the work together?
- Pipes X and Y can fill a tank in 45 minutes and 60 minutes respectively. Another pipe Z can empty the tank in 1 hour 30 minutes. If X and Z are opened firs...
8 men working 6 hours a day can complete a piece of work in 6 days. If efficiency of each woman is 20% more than that of each man, then how many women w...
- Alok finishes 60% of a project in 30 days, while Neha finishes 20% of the same in 15 days. Alok worked for 25 days and then stopped. Find the time taken by...