Question
How many persons are starting the business between B
and M? Study the following information carefully and answer the below questions. Eight persons- A, B, C, D, M, N, O and P are starting their business on different month- March, April, August and November on different dates either 06 or 17 of the month of the year 2020. All the information is not necessarily in the same order. O has started on April 17. Only one person is starting the business between M and N. P has started two persons before D. M has started the business on even numbered date after O. The number of persons starting between B and C is same as between N and D. A has started the business on either November or April. D has started on an odd numbered date. C does not start on even numbered date.Solution
O has started on April 17. M has started the business on even numbered date after O. Only one person is starting the business between M and N. From the above condition, there are three possibilities.
P has started two persons before D. D has started on an odd numbered date.
C does not start on an even numbered date. A is starting the business on either November or April.
The number of persons starting between B and C is same as between N and D. From the above condition, case1 and case3 get eliminated.
Case2 shows the final arrangement.
Â
Working alone, 'C' can complete a job in 30 days. 'D' takes 20% less time than 'C' to finish the same job. Calculate the percentage of work done by 'C' ...
- If Riya takes three times the time that Mahi takes or four times the time that Neha takes to finish a task, and all three working together can complete it ...
- Pipes X and Y can fill a water tank individually in 24 minutes and 36 minutes, respectively. A third pipe Z can empty the tank in 72 minutes. If all three ...
A can complete a piece of work in 24 days. He worked for 21 days and then B finished the remaining work in 6 days. In how many days can A and B finish t...
A can complete a piece of work in 10 days , and B can complete the same work in 15 days . They start working together, and after some days A leaves....
The ratio of time taken by P, Q and R to complete work alone is 4:6:3 respectively. If all three together complete the work in 8 days, then find in how ...
18 women can do piece of work in 12 days. 12 men can do the same piece of work in 9 days. Find in how many days will 8 men and 8 women complete that work?
A and B together, B and C together and A and C together can complete a piece of work in 14 days, 15 days and 18 days respectively. Find the ratio of the...
Q can do a work in 15 days and R can do the two-third work done by P and Q together in a day. If R completes the work in 18 days, how many days will it ...
A' can finish a job in 24 days, while 'B' is 25% less efficient than 'A.' If they take turns working, beginning with 'A,' how many days will it take for...