Question

A can complete a piece of work in 20 days. B is 25% more efficient than
A. C alone can complete the same work in 40 days. A and B work together for 6 days and then C alone finishes the remaining work. In how many days (total) is the work completed?

A 13 days
B 19 days
C 23 days
D 39 days