      Question

      Time taken by 18 men working 10 hours a day to complete

      a work is 28 days whereas time taken by 21 women working 8 hours a day to complete the work is 40 days. Find the time taken by 15 men and 20 women working together 12 hours a day to complete the work.
      A 16 days Correct Answer Incorrect Answer
      B 14 days Correct Answer Incorrect Answer
      C 18 days Correct Answer Incorrect Answer
      D 21 days Correct Answer Incorrect Answer
      E 12 days Correct Answer Incorrect Answer

      Solution

      Let the efficiency of a man and a woman be 'M' and 'W' units/day respectively. So, 18 X 10 X 28 X M = 21 X 8 X 40 X W Or, M:W = 4:3 Let 'M' = '4e' and 'W' = '3e' Let the required time be 'T' days. So, (15 X 4e + 20 X 3e) X 12 X T = 18 X 10 X 28 X 4e Or, 120 X 12 X T = 18 X 10 X 112 Or, 'T' = 14 days