      'P' completes a work in 18 days whereas 'Q' completes

      the work in 54 days. Both of them started the work together, but 'Q' left the work 6 days before the completion of work. Find the total time taken to complete the work.
      A 15 days Correct Answer Incorrect Answer
      B 18 days Correct Answer Incorrect Answer
      C 16 days Correct Answer Incorrect Answer
      D 12 days Correct Answer Incorrect Answer

      Solution

      Let the total work be 54 units (LCM of 18 and 54)

      Efficiency of 'P' = (54/18) = 3 units/day

      Efficiency of 'Q' = (54/54) = 1 unit/day

      Let the required time be 'T' days.

      So, 3 Ă— T + 1 Ă— (T - 6) = 54

      Or, 3T + T - 6 = 54

      Or, 4T = 60

      Or, 'T' = 15