      Question

      A can do a work in 12 days and B can do it in 18 days.

      In how many days will they finish together?
      A 8(1/3) days Correct Answer Incorrect Answer
      B 7(1/5) days Correct Answer Incorrect Answer
      C 2(2/7) days Correct Answer Incorrect Answer
      D 1(1/3) days Correct Answer Incorrect Answer

      Solution

      ATQ, Rate = 1/12 + 1/18 = 3/36 + 2/36 = 5/36 Time = 36/5 = 7 1/5 days