Question
A can complete a work in 15 days and B can complete the
same work in 20 days. They work together for 5 days. If after that B's efficiency increases by 25%, then in how many more days will B alone complete the remaining work?Solution
ATQ, A's 1-day work = 1/15 B's 1-day work = 1/20 Together = 1/15 + 1/20 = 4/60 + 3/60 = 7/60 Work done in 5 days = 35/60 = 7/12 Remaining work = 1 - 7/12 = 5/12 B's efficiency increases by 25% Original time of B = 20 days New time = 20/1.25 = 16 days New 1-day work of B = 1/16 Time to complete remaining work = (5/12) x 16 = 20/3
What is the main aim of the NOMADIC ELEPHANT exercise?
According to AMFI, mutual funds will deposit the redemption amount from equity schemes in investors’ bank accounts within ___ days of the transaction....
The Indian Institute of Spices Research (IISR) recently won the best technology award for its work in which field?
What was the theme for the 10th India Sweden Innovation Day in 2023?
On which date was the PM Internship Scheme App launched by Nirmala Sitharaman?
- Where is SECI’s 200 MW Solar Project being developed in Madhya Pradesh?
What is the total cost of the Porunai Archaeological Museum inaugurated in Tamil Nadu?
Which state is not part of the Nilgiri Biosphere Reserve?
Consider the following statements in regards to UDGAM portal:
1) It was launched by the RBI in Aug 2023.
2) It is a Centralised Web Portal...
What rank did Delhi’s Indira Gandhi International Airport achieve in the 2024 ACI Air Connectivity Ranking for Asia-Pacific and Middle East?