Question

‘U’ is 20% more efficient than ‘V’, and ‘W’ is 20% less efficient than ‘V’. Together, they can complete a job in 50 days. If U and V work together for 40 days, how many days will W take to finish the remaining work?

A 42 days
B 35 days
C 70 days
D 32 days
E None of these