πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!

  • google app store apple app store
  • βœ–

      Question

      30 men can complete a work in 12 days. After 9 days, 15

      more men joined them. How many days will they now take to complete the remaining work?
      A 3(1/2) days Correct Answer Incorrect Answer
      B 3(1/3) days Correct Answer Incorrect Answer
      C 3 days Correct Answer Incorrect Answer
      D 2days Correct Answer Incorrect Answer

      Solution

      Let, the efficiency of a man = y ATQ- (30 x y x 9) + (45 x y x D) = 30 x y x 12 (45 x y x D) = 360y-270y 45Dy=90y D = 90y/45y D=2 days.

      Practice Next

      Relevant for Exams:

      ask-question