Question
A civil contractor planned to build an over bridge of 3
km distance in 600 days. For this purpose, he employed 90 workers. After 200 days of work, it was observed that only 0.5 km of the bridge was completed. What is the number of extra workers required to complete the work on timeSolution
W1=1/6, W2=5/6 (M1 × D1× H1)/W1= (M2 × D2 × H2)/W2 (90 × 200)/1/6 = (M2 × 400)/5/6   M2 = 225  Þ Extra people = 225 – 90 = 135.
______ Test is used for checking integrity of Aseptic packaging material?
Which of the following is a dicotyledonous weed?
What does the conversion period in organic farming refer to?
Which of the following is the official certification mark for organic produce in India?
India’s agri export policy aims to double agricultural exports by which year?
The TBT agreement promotes which of the following principles?
Which online portal is used for FSSAI license application and compliance?
Which input helps improve soil organic carbon levels?
An acute or chronic inflammation of the mammary gland caused by physical, chemical and biological agents chiefly of bovines usually affecting the secret...
Which of the following is the apex body responsible for the promotion of agricultural exports in India?