Question
A civil contractor planned to build an over bridge of 3
km distance in 600 days. For this purpose, he employed 90 workers. After 200 days of work, it was observed that only 0.5 km of the bridge was completed. What is the number of extra workers required to complete the work on timeSolution
W1=1/6, W2=5/6 (M1 × D1× H1)/W1= (M2 × D2 × H2)/W2 (90 × 200)/1/6 = (M2 × 400)/5/6   M2 = 225  Þ Extra people = 225 – 90 = 135.
Source of trypisn enzyme is
Who discovered that the potato spindle tuber disease was caused by small naked ssRNA and called it a viroid?
Poultry industry is one of the largest and fastest growing livestock production systems in the world. The approximate nitrogen content in Poultry manure...
The correct order of crops with respect to their water requirement
The flash point of Biodiesel is:
MPTS stands forÂ
Most suitable crops for dry land are
If there is provision for only one irrigation, then at which stage in wheat the farmer should irrigate the crop?Â
CAS stands for
The net assimilation rate is expressed in terms