Question
A civil contractor planned to build an over bridge of 3
km distance in 600 days. For this purpose, he employed 90 workers. After 200 days of work, it was observed that only 0.5 km of the bridge was completed. What is the number of extra workers required to complete the work on timeSolution
W1=1/6, W2=5/6 (M1 × D1× H1)/W1= (M2 × D2 × H2)/W2 (90 × 200)/1/6 = (M2 × 400)/5/6   M2 = 225  Þ Extra people = 225 – 90 = 135.
The President is:
Social agreements are____________________
The Reserve Bank established under s.3 of the RBI Act, 1934 has taken over currency management from?
 What is the capital of Reserve Bank of India as per RBI Act, 1934?
Limitation act was enacted in the year:
Evidence in the proceedings of 125 of the Code of Criminal Procedure, 1973 shall be recorded in the manner:-
The special Judges appointed under the Prevention of Corruption Act shall try_________offences. Â
If the offence be punishable with imprisonment as well as fine, in case of default of payment of fine, the Court may direct imprisonment for a term whic...
Sec 12 of the Chhattisgarh rent control Act is related to:
Which of the following is not true about redemption?