A civil contractor planned to build an over bridge of 3
km distance in 600 days. For this purpose, he employed 90 workers. After 200 days of work, it was observed that only 0.5 km of the bridge was completed. What is the number of extra workers required to complete the work on timeSolution
W1=1/6, W2=5/6 (M1 × D1× H1)/W1= (M2 × D2 × H2)/W2 (90 × 200)/1/6 = (M2 × 400)/5/6   M2 = 225  Þ Extra people = 225 – 90 = 135.
In Excel typical worksheet has …. Number of columns
A half byte is know is
While studying about computer, we may came to know about the term QDR. Expand QDR?
A saved document is referred to as _________.
Word processing, spreadsheet, and photo-editing are examples of which type of software?
To print a document which shortcut is used?
Which of the following is a form of malware that encrypts a victim's files?
Which of the following Internet protocol specifies how data is exchanged over the Internet and how it should be broken into IP packets?
What happens when you press the "Insert" key on the keyboard?
Which sorting algorithm has a worst-case time complexity of O(n²)?