Question
Aβ and βBβ together can complete a work in 10 days
while βAβ takes 15 days to complete the same work alone. If βCβ is 20% more efficient than βBβ, then find the time taken by βCβ alone to complete the whole work.Solution
Let the total work = 30 units Efficiency of (A + B) = 30/10 = 3 units/day Efficiency of βAβ = 30/15 = 2 unit/day Therefore, efficiency of βBβ = 3 β 2 = 1 units/day Efficiency of βCβ = 1.2 Γ 1 = 1.2 units/day Required time taken = 30/1.2 = 25 days
What is the primary ethical concern when public officials engage in nepotism?
What leadership style focuses on involving employees in decision-making processes?
How can unethical practices impact a business's reputation and trust?
When a public official misuses public resources for personal gain, which ethical principle is violated?
What is the behavioral component of attitudes related to?
What do personal values guide?
Why is efficient stores management important for an organization?
What is an essential skill in successful negotiations?
What is the role of budgeting in financial management?
What is a critical step in project appraisal?