Start learning 50% faster. Sign in nowThe time ratio of P:Q:R = 4:3:6. Let their times be 4x, 3x, and 6x days. Together, they complete the work in 8 days. To find x:
Solving, we get x = 6. Find P’s Time 4x = 4×6 = 24 days Find Time for ¾ Work 3/4 ×24 = 18 days