Question
50 children can decorate a hall in 25 days. If 25 children began decorating and after 10 days ‘z’ additional children joined, completing the decoration in 20 more days, find ‘z’.
More Time and work Questions
- The ratio of efficiencies of Ajay and Bijay is 7:8, respectively. Ajay and Bijay together can complete the total work in 24 days. In how many days will Bij...
- A and B do some work, the efficiency of A is 25% more than that of B. If B does a piece of work in 10 days more than A. Then find out in how much time both...
- A and B together can complete a task in 40 days, while A alone takes 100 days to finish it. When A, B, and C work together, they can complete the task in 2...
- A can complete a work in 10 days and B can complete it in 15 days. They work together for 4 days, then A leaves. In how many days will B finish the remaini...
- 'P' and 'Q' can finish a piece of work in 45 days and 90 days, respectively. 'P' starts working alone, and 'Q' joins after 'r' days, ensuring that the enti...
- A work is done by A, B, C and D together. The percentage of work done by A, B C and D are in arithmetic progression (AP). The first, second, third and four...
- 8 men working 6 hours a day can complete a piece of work in 6 days. If efficiency of each woman is 20% more than that of each man, then how many women work...
- A and B can do a job in 20 days and 30 days, respectively. A and B work together for 5 days, and then A leaves. After how many more days will B complete th...
- ‘P’ can complete 80% of a task in 32 days and ‘Q’ can do 60% of the task in 54 days. If ‘P’, ‘Q’, and ‘R’ all work together, they can complete the full tas...
- ‘P’ takes 25 days to complete a piece of work. ‘Q’ is 25% more efficient than ‘P’. Find the time taken by them to complete 90% of the work together.
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)