Question
P and Q individually can complete the work in 18 days
and 27 days respectively. If the time taken by R alone to complete the work is 1.25 times the time taken by P and Q together to complete the work, find the time taken by R to complete the work while working alone. MTSolution
Time taken by P and Q together to complete the work = (18 × 27)/ (18 + 27) = 10.8 days Time taken by R alone to complete the work = 1.25 × 10.8 = 13.5 days
Meadow orcharding refers to
National Bureau of Animal Genetic Resources is located at ____
FAO stand for__________________
Sunflower and buckwheat are examples of!
Agricultural and Processed Food Products Export Development Authority was established by the Government of India in:
 In animal cell the reserve food is stored in the form of _____
 In woody plants and many fruits, transpiration takes place from:
Famine and drought are common feature of this Agro-climatic zone
Which of the following is citric acid soluble Phosphoric acid?
Cartilaginous fish are fish that have a skeleton made of cartilage. Cartilaginous fishes belong to: