Question
P and Q individually can complete the work in 18 days
and 27 days respectively. If the time taken by R alone to complete the work is 1.25 times the time taken by P and Q together to complete the work, find the time taken by R to complete the work while working alone. MTSolution
Time taken by P and Q together to complete the work = (18 × 27)/ (18 + 27) = 10.8 days Time taken by R alone to complete the work = 1.25 × 10.8 = 13.5 days
Which one is the example of Peripheral device?Â
What is the primary function of an AND gate in digital logic?
 In the design of a hard disk drive the motor driven spindle holds flat circular rotating discs which are known as __________ and onto which the data i...
 Which shortcut key is used to open a new window in chrome incognito mode in chrome ?
What does the acronym 'HTTP' stand for in web technology?
Name the software that is required to run any hardware component in a computer system.
Animation are created with ____________programs.
Which of the following is a multi-user System software (OS)?
It provides the basic structure for a particular kind of documents is known asÂ
EDVAC stands for_______