Question

    X men can complete the piece of work in 38 days and (X +

    40) men can complete the same work in 16 days less than that of days taken by X men. Find the value of X. 
    A 44 Correct Answer Incorrect Answer
    B 51 Correct Answer Incorrect Answer
    C 65 Correct Answer Incorrect Answer
    D 55 Correct Answer Incorrect Answer
    E 63 Correct Answer Incorrect Answer

    Solution

    According to question, => X × 38 = (X + 40) × 22 => 38X = 22X + 880 => 16X = 880 => X = 55