Question
A and B can do job in 6 days. B and C can do same job in
8 days. A, B and C together can do same job in 4 days. In how many days A and C together can complete the job?Solution
Total work = Number of days × 1 day’s work (efficiency) Total work = LCM (6, 8, 4) = 24 unit 1 day’s work of (A+B) = 24/6 = 4 unit 1 day’s work of (B + C) = 24/8 = 3 unit 1 day’s work of (A + B + C) = 24/4 = 6 unit Now, 1 day’s work of A = 6 – 3 = 3 1 day’s work of C = 6 – 4 = 2 1 day’s work of A and C = 3 + 2 = 5 A and C together can complete the job in = 24/5 = 4.8 days
Why is effective networking important in the workplace?
Why is tolerance important in a diverse society?
What is the purpose of stores management?
Why is perseverance important in achieving long-term goals?
What is the primary purpose of the "Golden Rule" in ethics?
What role does mentorship play in career advancement?
What ethical principle is violated when a public official engages in bribery or corruption?
What is the primary purpose of project appraisal?
Non-partisanship refers to:
What does job design focus on?