πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!

  • google app store apple app store
  • βœ–

      Question

      A and B together can complete a piece of work in

      30 days while A alone can complete 60% of the work in 45 days. Find the time taken by B to complete 74% of the work.
      A 37 days Correct Answer Incorrect Answer
      B 36 days Correct Answer Incorrect Answer
      C 32 days Correct Answer Incorrect Answer
      D 35 days Correct Answer Incorrect Answer
      E 30 days Correct Answer Incorrect Answer

      Solution

      Time taken by A to complete the whole work = 45/0.60 = 75 days
      Let total work = 150 units
      Amount of work done by A and B together in one day = 150/30 = 5 units
      Amount of work done by A alone in one day = 150/75 = 3 units
      Amount of work done by B in one day = 5 – 2 = 3 units
      Desired time = 0.74 × 150/3 = 37 days

      Practice Next
      ask-question