Question
P, Q, and R are racing on a
circular track with a length of 'd' meters. During the race, P finishes 800 meters ahead of Q and 1200 meters ahead of R. Likewise, Q finishes 600 meters ahead of R. The race lasts for 'r' rounds. Based on the given information, which of the following values cannot be 'r', assuming the track length is an integer?Solution
ATQ, Length of race = d X r = 'dr' metres Distance covered by Q in the time that P takes to cover dr metres = (dr - 800) metres And, distance covered by R in the time that P takes to cover dr metres = (dr - 1200) metres And, distance covered by R in the time that Q takes to cover dr metres = (dr - 600) metres ATQ; {(dr - 800)/(dr - 1200)} = {dr/(dr - 600)} Or, (dr - 600) X (dr - 800) = dr X (dr - 1200) Or, dr2 - 600dr - 800dr + 480000 = dr2 - 1200dr Or, 480000 = 200dr So, dr = 2400 So, r = {2400/d} Among given options, only 18 is not a factor of 2400. So, all the other options are possible answers.
Sachin can complete a job in 15 days. Ankit alone can complete the same job in 10 days. Sachin works for 9 days and then the remaining job is completed ...
A painter charges ₹500 for every hour of work. If he works for 6 hours a day and completes a project in 5 days, what is the total amount charged by th...
Ram can do a piece of work in 50 days. He alone worked at it for 20 days and then Lakshman completed alone the rest work in 30 days. In how many days, t...
P, Q, and R can complete a work in 12 days. 15 days and 30 days, respectively, working alone. How soon can the work be completed if P is assisted by Q a...
- If ‘X’ finishes a project in 24 days whereas ‘X’ and ‘Y’ working together can finish it in 15 days, then determine the time ‘Y’ alone will ...
"'Mahesh' is 40% less efficient than 'Neeraj.' 'Neeraj' takes 30 days fewer than 'Mahesh' to finish the same work. Find the time taken by 'Neeraj' to fi...
'A' can complete a certain task in 60 days, while 'B' can do the same in 45 days. 'A' starts the task and works alone for 18 days, after which 'B' joins...
A and B can finish a piece of work in 20 days and 30 days respectively. Both work on alternate days. In how many days will the work be completed when A ...
(x + 8) men working 9 hours a day can complete 60% of a work in 12 days. (x + 2) men working 3 hours a day can complete the remaining work in 32 days. F...
A is half as efficient as B. C does half as much work as A and B together. If c alone can do the work in 40 days. Then in how many days will A, B and C ...