Question
Mixture βXβ contains 50% alcohol and the rest 40
litres of water. 150 litres of mixture βYβ contains alcohol and water in the ratio 5:10, respectively. Find the resultant ratio of alcohol to water when these two mixtures are mixed.Solution
ATQ, Quantity of alcohol in mixture βXβ = 40 Γ (0.5/0.5) = 40 litres Quantity of alcohol in mixture βYβ = 150 Γ (5/15) = 50 litres Quantity of water in mixture βYβ = 150 β 50 = 100 litres Total quantity of alcohol in resultant mixture = 40 + 50 = 90 litres Total quantity of water in resultant mixture = 40 + 100 = 140 litres Required ratio = 90:140 = 9:14
Nikhil and Rohit together can complete a job in 105 days 8 minutes, while Rohit and Suresh together can finish the same job in 70 days 5 minutes. If Sur...
Worker 'A' can complete the entire task in 35 hours, and Worker 'B' can complete it in 40 hours, when working individually. If both 'A' and 'B' work tog...
A and B together can complete a piece of work in 35 days while A alone can complete 50% of the work in 20 days. Find the time taken by B to complete 12....
Two workers, βXβ and βYβ, can finish a job in 25 days together. If βXβ is 25% more efficient than βYβ, find the number of days βYβ a...
Shivam and Harish can do a job alone in 90 days and 120 days respectively. Both work together and earn Rs. 5,250. Find Shivamβs earnings.
A and B finish a job together in 36 days, while B and C together finish it in 48 days. The trio completes 75% of the job in 18 days. In how many days wi...
Anil, Sunil, and Rajesh can complete a project working alone in 6, 8, and 12 days, respectively. If they all work together to complete the project and e...
8 children and 6 women together can complete a piece of work in 10 days and work done by a children in one day is one-third of the work done by a women ...
Aβ and βBβ together can complete a work in 22 days while βAβ takes 33 days to complete the same work alone. If βCβ is 20% more efficient t...
- Meena alone can complete a work in 20 days. Ritu is twice as efficient as Meena. Find the percentage of work completed by Meena and Ritu together in 4 days...