Question
In which of the following cases, the Supreme Court of
India has enumerated the rights of an arrestee?Solution
D.K. Basu v. State of West Bengal is a landmark judgment given by the Apex court in the case of an increasing number of custodial deaths in India. The executive chairman of legal aid services wrote a letter against the increasing number of cases of custodial deaths and this letter was treated as a writ petition by the court by taking into consideration the gravity of the issue. The court observed that custodial death is a matter of concern and it is more aggravated as it is committed by the protector of the citizens. Thus, it was held by the court that this act is against Art. 21 and 22 of the Constitution of India. It is in clear transgression of the victim’s fundamental rights and human dignity. It was also observed by the court that the use of third-degree methods by police is illegal and should not be used to extract the information from the accused and held that majesty of the law must prevail. Court also observed that recommendations suggested by the law commission report must be adopted by the government to curb these offenses against humanity.
Anil and Ashish receive Rs.2000 for work of 8 days. If Anil is 4 times efficient than Ashish, then find the daily wage received by Ashish.
- Together, Ali and Imran take 40 days to complete a project. After working jointly for 32 days, they left, and Zara completed the remaining work in 4 days. ...
'B' is 20% more efficient than 'A.' 'A' began working on a task alone and continued for 8 days, after which 'B' took over and completed the remaining wo...
- A builder employed 12 workers to complete a job in 18 days. But after 8 days, 4 workers quit. How many more days will be required to complete the remaining...
‘A’ can do a piece of work in 8 days. ‘B’ can do 40% of the same work in 16 days. If they work together for the entire time and get paid Rs.1500...
A contractor hired 50 workers to complete a work in 80 days. After 50 days, it was found that only 1/4th of the work was completed. Find the number of e...
A and B can do a piece of work in 12 days and 18 days, respectively. They start working together, and after 4 days, A leaves the work. How many more day...
‘A’ alone can complete a work in 40 hours. ‘A’ started the work alone and left after working on it for 20 hours. If ‘B’ completed the rest o...
If a group of 20 boys and 10 girls can finish a task in 50 days, and a team of 8 girls alone can complete the same task in 120 days, how long will it ta...
Anil and Ashish receive Rs.1200 for work of 8 days. If Anil is 5 times efficient than Ashish, then find the daily wage received by Ashish.