Question
βAβ alone can complete a work in 40 hours. βAβ
started the work alone and left after working on it for 20 hours. If βBβ completed the rest of the work in 20 hours then find the time taken by βAβ and βBβ together to complete the whole work.Solution
Let the total work = 300 units Then, efficiency of βAβ = (300/40) = 7.5 units/hour Work completed by βAβ alone in 20 hours = 7.5 Γ 20 = 150 units Remaining work = 300 β 150 = 150 units So, efficiency of βBβ = 150/20 = 7.5 units/hour Therefore, combined efficiency of βAβ and βBβ = 7.5 + 7.5 = 15 units/hour So, time taken by βAβ and βBβ together to complete the work = (300/15) = 20 hours
64.5% of 800 + Β 36.4% of 1500 = (?)Β² + 38
β256 * 3 β 15% of 300 + ? = 150% of 160
82% of 400 + √(?) = 130% of 600 - 85% of 400
25% of 140 + 2Β ΓΒ 8 = ? +Β 9Β ΓΒ 5
- What will come in place of the question mark (?) in the following questions?
120Γ·(5Γ2)+8=? 4.7 × 3.5 + 4.2 × 4.5 = 22.5 × 3.5 - ?
180 Γ· 3 ofΒ 2 = 102 β ?
36 Γ 15 + 20% 1250 = ? + 296
(1296)Β -3/4Β = ?