Question
βAβ alone can complete a work in 40 hours. βAβ
started the work alone and left after working on it for 20 hours. If βBβ completed the rest of the work in 20 hours then find the time taken by βAβ and βBβ together to complete the whole work.Solution
Let the total work = 300 units Then, efficiency of βAβ = (300/40) = 7.5 units/hour Work completed by βAβ alone in 20 hours = 7.5 Γ 20 = 150 units Remaining work = 300 β 150 = 150 units So, efficiency of βBβ = 150/20 = 7.5 units/hour Therefore, combined efficiency of βAβ and βBβ = 7.5 + 7.5 = 15 units/hour So, time taken by βAβ and βBβ together to complete the work = (300/15) = 20 hours
Β Bajrang Punia is related to which sport?
Which Indian mobile phone brand has become the first one to launch 5G smartphones for its domestic customers?
In which Hindu month is Nag Panchami celebrated?
What is USSD in mobile industry?
The Reserve Bank of India plans to implement a 5% run-off factor on digitally accessible retail deposits to manage what type of risk?
In the Economic Survey 2021-22,Β India registered its highest-ever annual FDI inflow of _____ dated 31 Jan 2022.
Where is the Headquarters of the North Atlantic Treaty Organization (NATO)?
Match the following Days with their respective daysΒ Β Β

The 2nd phase of 36 βSaansad Khel Mahakumbh 2022-23β has been inaugurated in which district of the state Uttar Pradesh?
A privately held company can go with FPO for raising money from the market.