Question
‘A’ alone can complete a work in 40 hours. ‘A’
started the work alone and left after working on it for 20 hours. If ‘B’ completed the rest of the work in 20 hours then find the time taken by ‘A’ and ‘B’ together to complete the whole work.Solution
Let the total work = 300 units Then, efficiency of ‘A’ = (300/40) = 7.5 units/hour Work completed by ‘A’ alone in 20 hours = 7.5 × 20 = 150 units Remaining work = 300 – 150 = 150 units So, efficiency of ‘B’ = 150/20 = 7.5 units/hour Therefore, combined efficiency of ‘A’ and ‘B’ = 7.5 + 7.5 = 15 units/hour So, time taken by ‘A’ and ‘B’ together to complete the work = (300/15) = 20 hours
Which of the following potential is always negative?
In CRD design the degree of freedom for error is calculated by which formula?
Marconi wheat is known as:
Which crop is called 'camel crop"?
The synthesis of ATP via electron flow through the ETS, with oxygen as the terminal electron  acceptor,   is  known...
According to latest Final estimates of Foodgrain production 2023-24, Which state is the largest producer of sugarcane in India?
Tikka disease of groundnut spreads fast under the conditions of:
Pradhan Mantri Krishi Sinchai Yojana (PMKSY) was launched in the year___
What is the meaning of the word "Chrysanthemum," as derived from its etymology?
Of which South-East-Asian country did Joko Widodo become the President in 2019 for the second time?