- Aman and Bhuvan can complete a work in 21 days together, while Bhuvan alone can do it in 35 days. If the ratio of efficiencies of Aman and Chintu is 2:3, f...
Ram, Ankit and Shivam together can do a piece of work in 10/3 days. Ram could do it alone in 6 days and Ankit could do it alone in 12days. In how many d...
Komal and Seema individually can complete a task in β2aβ hours and β7aβ hours respectively. If they together can complete halfΒ of the work in 7...
X men can complete the piece of work in 32 days and (X + 30) men can complete the same work in 15 days less than that of days taken by X men. Find the v...
βAβ is 50% less productive compared to βBβ, who is 20% more productive than βCβ. Together, they can finish a task in 36 days. After βBβ ...
Pβs 4 days work is equal to Qβs 5 days work. If P and Q together can complete the work in 25 days then how much time Q will take to complete 40% of ...
Peter and Rachel can complete a project together in 20 days. Peter takes four times as long as Rachel to complete the same project alone. Find the time ...
Amisha is 50% more efficient than Khushi. Amisha started a work, worked for 'w' days and then Khushi replaced Amisha. khushi completed the remaining wor...
βAβ and βBβ can do a piece of work in 20 days and 30 days, respectively. If they started the work together and worked on it for 7 days, then fin...
A and B can complete a task together in 22 days, while B alone takes 44 days to finish it. A began working alone and left after βxβ days, after whic...