Question
Which of the following is the correct Function –
Day combination? Study the following information and answer the questions based on it. 1. A banquet hall is booked for six continuous days for different functions (Birthday, Anniversary, Wedding, Reception, Farewell, Engagement, Sangeet ceremony, Mehendi ceremony, Haldi ceremony, Conference, Cocktail party and Retirement party) not necessarily in the same order. These functions are to be held either in the morning slot or in the evening slot through 6 days starting from Monday up till Saturday. 2. Only two functions are held before Birthday party. 3. Sangeet to be held on the last day. 4. Farewell to be held only before two functions. Cocktail party to be held in the same slot as the farewell. 5. Haldi ceremony to be held before conference and reception but not on Monday. Slots for all three are the same. 6. Conference is not to be held on Saturday. 7. The number of functions between Engagement and anniversary are same as the number of functions between cocktail and reception. But, Engagement is not held after reception. 8. Wedding is held on the same day of the Anniversary party. Retirement party to be held on the same day as the reception party and in the same slot as the birthday party.Solution
From 1,2,3 From 8, Retirement party to be held on the same day as the reception party and in the same slot as the birthday party. But since Haldi is to be held before reception and conference, neither reception, retirement party nor Conference can be held on Monday. Also, Haldi not be held on Monday and Conference is not to be held on Saturday. Thus,
Dividing the above table in two cases for better understanding. Case I – Conference on Wednesday Case II - Conference on Thursday
Wedding is held on the same day of the Anniversary party. Also Cocktail is an evening function. Thus, Sangeet must be held in the morning
The number of functions between Engagement and anniversary are same as the number of functions between cocktail and reception.
Final arrangement as shown below: 
P can do a piece of work in 15 days, Q can complete double the work in 40 days and R can do the work in 20 days. If all of them together earn Rs. 3000, ...
- Alex and Ben can complete a job individually in 14 days and 21 days, respectively. If they take turns to work one day each, beginning with Alex, how long w...
βXβ and βYβ can do a task together in 15 days. If βXβ alone takes 25 days to complete it, then how much time will βYβ take to finish the...
βPβ and βQβ can complete a task together in 24 days. If βPβ alone can do it in 40 days, find the number of days βQβ alone will take to f...
A can complete a work in 40 days. B takes 20 days less than A to complete the same work. In how many days can both of them together complete 90% of the ...
P can do a piece of work in 30 days. Q do the same work in 40 days. R can do it in 35 days. P and R worked for 4 days and handed it to Q. Q worked for s...
X can do a piece of work in 15 days. He worked at it for 3 days and then Y finished it in 16 days. In how many days can X and Y together finish the work?
A job is done by 15 men in 30 days and 30 women in 20 days. How many days will it take for 8 men and 12 women to finish the work?
P can do a piece of work in 20 days, Q can do the same piece of work in 24 days while R can do it in 30 days. They started working together but after 4 ...
12 engineers complete designing 180 blueprints in 15 days. If the goal is to complete 270 blueprints in 18 days, how many engineers are required?