    Question

    Dhamu can complete a task on his own in 10 days. When

    Dhamu collaborates with Gaja, they can finish the same task in 6 days. Determine the number of days it would take for Gaja to complete 50% of the task by himself.
    A 7(1/2) days Correct Answer Incorrect Answer
    B 8(1/2) days Correct Answer Incorrect Answer
    C 6(1/2) days Correct Answer Incorrect Answer
    D 5(1/2) days Correct Answer Incorrect Answer

    Solution

    Let total work = 30 units Efficiency of Dhamu = (30/10) = 3 units/day Combined efficiency of Dhamu and Gaja = (30/6) = 5 units/day Therefore, efficiency of Gaja = 5 - 3 = 2 units/day Required number of days taken =┬а (0.50 x 30)/2 = 15/2 = 7(1/2) days