20 workers are employed to complete a work in 40 days.
But some workers leave the job after 16 days of work. The remaining workers complete the work in 46 days from its beginning. How many workers left the job after 16 days? type-sscSolution
D₁ = (40-16) = 24 D2=(46-40) =6 Let the M1=x and M2=x-4 M₁D₁ = M2 D2 X × 24 = (20-x) ×6 4x=20-x 5x=20 x=4 Hence, after 16 days 4 workers left work.
Who lives immediate below P?
C visited the city on which of the following day of the week?
What is the position of E with respect to D?
Four of the following five are vishal in a certain way and hence form a group. Which is the one that does not belong to the group?
In each of the following questions, select the related word from the given alternatives:
OFFICE : QHHKEG ::WORKER : ?
Four of the following forms a group based on certain pattern. Who does not belong to this group?
Who among the following person visited on 9 May?
If D is related to Jaipur and G is related to Chennai in a certain way. Then, B is related to which of the following?
Who among the following live on topmost floor?
How many teams play between the teams which play game R and W?