Question
A and B working together completed a job in 40/9 days. If A had worked twice as efficiently as she did and B had worked 1/3 of his actual efficiency, then the work would have been completed in 60 /17 days. Find the time A would take to complete the work alone.
More Time and work Questions
- Karan can do 80% works in 40 days. Remaining work completed by Karan and Arjun in 6 days. In how many total days the total work is finish if Arjun work alo...
- ‘A’ and ‘B’ can do a piece of work in 20 days and 40 days, respectively. If they started the work together and worked on it for 6 days, then find the time ...
- Together, Ali and Imran take 40 days to complete a project. After working jointly for 32 days, they left, and Zara completed the remaining work in 4 days. ...
- A and B together can complete a piece of work in 12 days while A alone can complete 70% of the work in 14 days. Find the time taken by B to complete 80% of...
- Gagan can do a piece of work in 14 days. Magan is 40% more efficient than Gagan. How many days will Magan and Gagan together complete the work?
- 25 employees working 9 hours a day take 20 days to complete a project. How many employees working for 8 hours a day are needed to complete twice the given ...
- Shudhanshu completes 1/2 of work in 12 days, then he completes the remaining work with the help of Neeraj in 5 days. The time required for Sudhanshu and N...
- Riya can do a piece of work in 30 days, and Mehul can do it in 45 days. Find the number of days Kabir will take to complete the job if he is 20% more effic...
- 'A' and 'B' together can do a piece of work in 12 days while 'B' and 'C' together can do the same work in 16 days. 'A' started the work alone and worked on...
- Working together, A and B can do a certain work in 45 days. They work together for 10 days. They complete the remaining work in 28 days with the assistance...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)
20A=25B A/B=25/20 A/B=5/4 A: B=5:4 ATQ- Total work= (40/9) ×9 =40 Total work completed by A = 40/5=8 days