Question
βMβ is 60% more efficient than βNβ. βNβ
started the work alone and worked for 20 days and after that βNβ is replaced by βMβ. If the total work is completed in 46 days, find the time taken by βMβ to finish the same work alone?Solution
Let the efficiency of βNβ = β5xβ units/day Efficiency of βMβ = β8xβ units/day Time taken by βMβ to complete the remaining work = 46 β 20 = 26 days Total work = 20 Γ 5x + 26 Γ 8x = 308x units Desired time = 308x/8x = 38.5 days
The Chambal, Hindon and Tons rivers are tributaries of the river:
What is Indiaβs rank in global biodiversity conservation?
Which of the following countries is not included in the South Asian Association for Regional Cooperation Organization (SAARC)?
Which of the following countries emerged as the top three for Foreign Direct Investment (FDI) equity inflows into India in descending order during the f...
Indian National Space Promotion and Authorization Centre (INβSPACe) is a single-window autonomous agency under the Department of Space. Who is the cur...
Which of the following Marine Protected Areas (MPAs) are located in Peninsular India and play a vital role in conserving marine biodiversity and support...
In India, 30th January is celebrated as:
What is the primary purpose of the SEWA Portal introduced by the Indian government? Β
Which among the following books is not written by Arundhati Roy?
As per the Reserve Bank of India (RBI) data, the bank credit growth stood at ____ %, meanwhile deposits grew by 9.2%.