Question
βMβ is 60% more efficient than βNβ. βNβ
started the work alone and worked for 20 days and after that βNβ is replaced by βMβ. If the total work is completed in 46 days, find the time taken by βMβ to finish the same work alone?Solution
Let the efficiency of βNβ = β5xβ units/day Efficiency of βMβ = β8xβ units/day Time taken by βMβ to complete the remaining work = 46 β 20 = 26 days Total work = 20 Γ 5x + 26 Γ 8x = 308x units Desired time = 308x/8x = 38.5 days
Under which of the following scheme, the Centre transfers an amount of Rs 6,000 per year, in three equal instalments?
The EPCG scheme is governed by the Foreign Trade Policy of India and administered by which of the following government body?
Match the following:
Which of the pairs given above i...
Which International Organisation provides Emergency Use Listing (EUL) status for various Covid vaccines worldwide.
The upper limit for FDI in Insurance Sector is increate to ____ % from 49%.
The reportΒ World Economic Outlook is released by which organization ?
Which of the following statements best describes/ describe the term βCore Banking Solutionsβ?Β
1. It is a networking of a bankβs branches ...
US President Joe Biden has elevated Indian-American political advisor Gautam Raghavan as _______________.
What are the three layers of open APIs in India Stack, enabling governments, businesses, startups, and developers to utilize a unique digital infrastruc...
With reference to the North Atlantic Treaty Organization (NATO), consider the following statements:
I.NATO is a political and military alliance.<...