Question
‘M’ is 60% more efficient than ‘N’. ‘N’ started the work alone and worked for 20 days and after that ‘N’ is replaced by ‘M’. If the total work is completed in 46 days, find the time taken by ‘M’ to finish the same work alone?
More Time and work Questions
- Shivam invested 25000 at 12% p.a. simple interest for ‘x’ months. If at the end of ‘x’ months, he received a total amount of Rs.30000. What is the value of...
- 15 men can complete a piece of work in 5 days, while 20 women can complete it in 5 days. 8 men start working on the job & after working for 3 days, all of ...
- Akhil and Nikhil together can complete a work in 12 days while Nikhil alone takes 18 days to complete 25% of the work. If the efficiency of Sachin is 20% m...
- 40 men take 15 days to finish some work. If the work is to be finished in 8 days, then how many additional men should be hired?
- Two workers A and B were put to some work. If A worked alone, he would have taken 8 hours more than when both A and B had worked together. If B worked alon...
- A Mahalaxmi tourist bus with only the driver inside has a speed of 60 kmph. Its maximum speed reduces by a quantity which is directly proportional to the n...
- A can fabricate a divider in 10 days , while B alone can assemble it in 30 days, If they construct it together and get an installment of Rs 8200, then find...
- Armaan can complete a task in 36 days, Bittu in 45 days, and Chirag in 60 days. If Bittu and Chirag together work on the task for 10 days, how many additio...
- A and B together can complete a work in 10 days. B alone can complete the same work in 25 days. In how many days can A alone complete the work?
- A and B together can complete a piece of work in 12 days. B and C together can complete it in 16 days. C and A together can complete it in 24 days. They al...
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt