📢 Too many exams? Don’t know which one suits you best? Book Your Free Expert 👉 call Now!

  • google app store apple app store
  • ✖

      Question

      50 men takes 10 less days to do a work than 30 men takes

      time for same work. Find in how many days 15 men can complete the 2/5th of the work?
      A 18 days Correct Answer Incorrect Answer
      B 20 days Correct Answer Incorrect Answer
      C 12 days Correct Answer Incorrect Answer
      D None of these Correct Answer Incorrect Answer

      Solution

      ATQ, Let 30 men takes time = x days Then, 50 men will take (x-10) days In both the conditions work done will be same 30x = 50(x-10) X = 25 Total work has to be done = 30x = 30 × 25 = 750 unit Work has to be done by 15 men = 2/5 × 750 = 300 unit Time taken by 15 men = 300/15  = 20 days

      Practice Next
      ask-question