Question
A 40 hectare field is reaped by 4 men, 6 women and 8
children together in 10 days. If working capabilities of a Man, a Woman and a Child are in the ratio 6: 5: 4, then a 60 hectare field will be reaped by 12 Men, 8 Women and 15 Children in how many days?Solution
According to the question, Efficiency of Men, Women and Children = 6 : 5 : 4 units/day One day work of 4 Men = 4 × 6 = 24 units One day work of 6 Women = 6 × 5 = 30 units One day work of 8 Children = 8 × 4 = 32 units Let time taken by 12 Men, 8 Women and 15 Children be ‘D’ days By applying formula, ((24+30+32)×10)/40 = [(((12×6)+ (8×5)+(15×4))×D)/60] 860/40 = ((72+40+60)×D)/60 860/2 = (172×D)/3 D = (860×3)/(2×172) = 7(1/2) days
Ravi and Rekha, alone can complete a work in 25 days and 50 days, respectively. They started the work together and left after 10 days such that the rema...
A alone can finish a piece of work in 10 days and B alone can finish it in 15 days. They work together for 3 days and the remaining work is finished by ...
P, Q & R can finish a work in 10 days, 15 days, and 20 days, respectively, working alone. P and Q work on the first day, P and R work on the second day,...
(x + 6) workers complete 40% of a job in 8 days by working 5 hours/day. The remaining work is done by (x + 2) workers in 16 days working 5 hours/day. Fi...
Amin, Basha and Cheez can do a piece of work in 90, 40 and 12 days respectively. But they decide. That a single person will work in a day and receive Rs...
138 unit of work can be completed by P alone in 23 days. P started working alone and joined by Q after 11 days such that they completed the remaining wo...
- Two workers, A and B, can finish a task in 36 days and 48 days respectively, working alone. How many days will they take to complete the work together?
- Pipes X and Y can fill a tank in 45 minutes and 60 minutes respectively. Another pipe Z can empty the tank in 1 hour 30 minutes. If X and Z are opened firs...
8 men working 6 hours a day can complete a piece of work in 6 days. If efficiency of each woman is 20% more than that of each man, then how many women w...
- Alok finishes 60% of a project in 30 days, while Neha finishes 20% of the same in 15 days. Alok worked for 25 days and then stopped. Find the time taken by...