Question
'X' and 'Y' can complete a certain job together in 36
days. They worked together for 20 days, after which 'X' left, and 'Y' completed the remaining work alone in 40 days. Determine the amount of time it would take for 'Y' to finish the entire job if he worked on it alone from the start.Solution
Let the efficiency of 'X' and 'Y' be 'x' units/day and 'y' units/day, respectively. ATQ; 36 × (x + y) = 20 × (x + y) + 40y Or, 36x + 36y = 20x + 60y Or, 16x = 24y So, x = (3y/2) So, total work = 36 × {(3y/2) + y} = 36 × (5y/2) = '90y' units So, required time = 90y ÷ y = 90 days Alternate Solution Part of the work completed by 'X' and 'Y' together in 20 days = (20/36) = (5/9) Remaining part of the work = 1 - (5/9) = (4/9) which is completed by 'Y' alone in 40 days Therefore, time taken by 'Y' to complete the whole work alone = 40 ÷ (4/9) = 40 × (9/4) = 90 days
Four terms are in proportion. The first, second and fourth terms are 4, 22, and 33. Find the third term.
4Â Â Â Â Â Â Â Â Â Â Â Â Â Â 7Â Â Â Â Â Â Â Â Â Â Â Â Â Â 24Â Â Â Â Â Â Â Â Â Â Â 91Â Â Â Â Â Â Â Â Â Â Â 462Â Â Â Â Â Â Â Â Â 2763
18Â Â Â ...
A series is 11, 20, 42, 82, 166, 330
If another series 4, a, b, c, d, 106 follows the same pattern as the given number series, then find the appr...
12, 24, 72, 288, 1440, ?
60  61  126  387  ?   7845
315 146 267 ? 235 210
Three series are given below. You have to find the values of P, Q and R, then establish a relationship among them.
I:Â Â 840, P , 584, 456, 5...
28 34 63 ? 769 3847
...105   107   111   114   ?   127
4 5.5 19 .5 98.5 694 6251.5
...