Question
'X' and 'Y' can complete a certain job together in 36
days. They worked together for 20 days, after which 'X' left, and 'Y' completed the remaining work alone in 40 days. Determine the amount of time it would take for 'Y' to finish the entire job if he worked on it alone from the start.Solution
Let the efficiency of 'X' and 'Y' be 'x' units/day and 'y' units/day, respectively. ATQ; 36 × (x + y) = 20 × (x + y) + 40y Or, 36x + 36y = 20x + 60y Or, 16x = 24y So, x = (3y/2) So, total work = 36 × {(3y/2) + y} = 36 × (5y/2) = '90y' units So, required time = 90y ÷ y = 90 days Alternate Solution Part of the work completed by 'X' and 'Y' together in 20 days = (20/36) = (5/9) Remaining part of the work = 1 - (5/9) = (4/9) which is completed by 'Y' alone in 40 days Therefore, time taken by 'Y' to complete the whole work alone = 40 ÷ (4/9) = 40 × (9/4) = 90 days
A alone can complete a work in 18 days and B alone can complete it in 27 days. They work together for 6 days and then B leaves. In how many more days wi...
- Rahul does half the work done by Karan in 2/3 of the time. If they together can complete the work in 14 days, how much time will Karan take to complete the...
‘A’ alone can do some work in 20 days. ‘B’ and ‘C’ together can do the same work in 15 days. If ‘B’ is half as efficient as ‘A’, the...
Ashish and Anil can do a piece of work in 18 days and 24 days respectively. Ashish completed 25% of the work. Find the time taken by Anil to complete th...
Akhil and Nikhil together can complete a work in 9 days while Nikhil alone takes 12 days to complete 50% of the work. If the efficiency of Sachin is 20%...
- 45 engineers working 5 hours a day take 15 days to complete a project. How many engineers working for 4 hours a day are needed to complete three times the ...
A, B, and C can complete a job in 15, 20, and 30 days, respectively. They start the work together but after 3 days, A leaves. Then, B works alone for 5...
P and Q together can finish a task in 72 days while Q and R can do it in 48 days. If P worked for 18 days, Q worked for 30 days, and then R finished the...
- 'Amit', 'Ravi', and 'Neha' can finish a piece of work in 66, 99, and 132 days respectively. They all started the work, but Amit left 8 days before the work...
A and B can complete a work together in 20 days. If A alone can complete one-fourth of the work in ‘x’ days and remaining work is completed by B alo...