Ravi appointed 24 workers to finish a job in 18 days.
After 9 days, he saw that only 1/3 of the job was completed. If 'n' is the number of additional workers required to complete the work on time, how many prime numbers are there which are less than or equal to (n/2)?Solution
ATQ,
Work done = 24 Γ 9 Γ 10 = 2160 Only 1/3 of work done, so total work = 2160 Γ 3 = 6480 Remaining work = 6480 β 2160 = 4320 Time left = 9 days Let additional men = n β total men = 24 + n (24 + n) Γ 9 Γ 10 = 4320 β (24 + n) Γ 90 = 4320 β 24 + n = 48 β n = 24 Then, n/2 = 12 Prime numbers β€ 12: 2, 3, 5, 7, 11 Total = 5 prime numbers
On a graph for a monopolist or monopolistic competitor, which of the following curves coincide?
The equation for a supply curve is P = 3Q β 8. What is the elasticity in moving from a price of 4 to a price of 7?
Individuals can now directly purchase treasury bills, dated securities, sovereign gold bonds (SGB) and state development loans (SDLs) under RBIβs ___...
In the Classical model, if there is an increase in aggregate demand, what will be the long-run effect on output and prices?Β
Consider the following:
Assertion (A): According to Peacock-Wiseman hypothesis, public expenditure increases overtime in a step-by-step manner.
Which of the following is not an example of market failure?
What does the Purchasing Managers' Index (PMI) measure?
The credit manager at a Departmental store collects data on 100 of her customers. Of the 60 men, 40 have credit cards (C). Of the 40 women, 30...
In the Classical model, what is the shape of the Aggregate Supply (AS) curve in the long run, and why?
An investor who expects a stock price to fall significantly might use which strategy?