      Question

      Quantity-I: 'C' can do 30% of work in 18 hours. Find

      the value of 'Y' if the time taken by him to complete the whole work is 'Y' hours. Quantity-II: What is the value of 'X' in the given series: 47, 49, 52, 57, 64, 'X'?
      A Quantity-I > Quantity-II Correct Answer Incorrect Answer
      B Quantity-I < Quantity-II Correct Answer Incorrect Answer
      C Quantity-I ≤ Quantity-II Correct Answer Incorrect Answer
      D Quantity-I = Quantity-II or No relation Correct Answer Incorrect Answer
      E Quantity-I ≥ Quantity-II Correct Answer Incorrect Answer

      Solution

      Quantity I: Y = (18/30) × 100 = 60 So, Quantity I = 60 Quantity II: The given series is: number + consecutive prime numbers starting from '2'. 47 + 2 = 49 49 + 3 = 52 52 + 5 = 57 57 + 7 = 64 64 + 11 = 75 So, X = 75 So, Quantity II = 75 So, Quantity I < Quantity II