Question
Quantity I: A and B can complete a work together in 12
days. After working together for 6 days, A leaves, and B finishes the remaining work in 10 more days. How many days would it take for A alone to complete the entire work? Quantity II: C and D together can complete a job in 15 days, but if C worked alone, he would take 24 days. D worked alone for 6 days before C joined to complete the remaining job together. How many days in total did it take to finish the work?Solution
Quantity I: Let the total work be 1 unit. Combined rate of A and B = 1/12 units per day. In 6 days, they complete 6 * (1/12) = 1/2 of the work. Remaining work = 1 - 1/2 = 1/2 unit, which B completes in 10 days. Bβs rate = (1/2) / 10 = 1/20 units per day. Rate of A alone = (1/12) - (1/20) = (5 - 3)/60 = 1/30 units per day. Time taken by A alone to complete the work = 1 / (1/30) = 30 days. Quantity II: Let the total work be 1 unit. Combined rate of C and D = 1/15 units per day. Cβs rate alone = 1/24 units per day, so Dβs rate = (1/15) - (1/24) = 1/40 units per day. D worked alone for 6 days, completing 6 * (1/40) = 3/20 of the work. Remaining work = 1 - 3/20 = 17/20. Time for C and D together to complete 17/20 work = (17/20) / (1/15) = (17/20) * 15 = 12.75 days. Total time = 6 + 12.75 = 18.75 days. Answer: A (Quantity I < Quantity II)
The amount of work completed by 24 men in 5 hours is equivalent to the work done by 21 women in 8 hours. A team of 33 men, working 6 hours daily, can fi...
βAβ and βBβ can do a piece of work in 15 days and 20 days, respectively. They started working together but βAβ left after 3 days. Find the t...
P can do a piece of work in 25 days, Q can complete double the work in 40 days and R can do the work in 30 days. If all of them together earn Rs. 7400, ...
βAβ alone can complete a work in 50 hours. βAβ started the work alone and left after working on it for 30 hours. If βBβ completed the rest o...
A and B individually can complete the work in 28 days and 42 days respectively. If the time taken by C alone to complete the work is 1.25 times the time...
βAβ alone can complete a work in 12 days. βBβ alone can complete the same work in 20 days. If βAβ and βBβ work together for 6 days, then...
Puneet and Qureshi together can complete (7/8)th of a piece of work in 9 days, Qureshi and Rohit together can complete (3/5)th of the work in 8 days and...
The time taken by βAβ to complete a task is 6 days more than the time taken by A and B together. If A is twice as efficient as B, find the time requ...
βDβ and βEβ together can finish a task in 40 days, while βEβ and βFβ together can finish the same task in 30 days. βDβ and βEβ t...
45 men can complete 3/5 part of a work in 8 days working 9 hours a day. How many women can complete rest of the work if they work for 6 hours a day for ...