Question

    Benny can do a piece of work in 24 days. Chethan and

    David can do the same work individually in 36 and 48 days, respectively. All of them begin the work together. However, Benny leaves the work 4 days before the completion of work and Chethan leaves the work 10 days before the completion of the work. David worked till the end and completed the work. Find the number of days in which the work was completed.
    A 16 Correct Answer Incorrect Answer
    B 20 Correct Answer Incorrect Answer
    C 18 Correct Answer Incorrect Answer
    D 15 Correct Answer Incorrect Answer

    Solution

    The correct answer is A