Question
105 people could complete a work in 36 days. But after they worked together for 8 days their employer wanted that the work should be completed in a total of 29 days. How many more workers need to be employed to meet the deadline?
More Previous year papers Questions
- When folded into two equal halves, a rectangular sheet had a perimeter of 36 cm for each part folded along one set of sides, and the same is 45 cm when fo...
- Question 2
- A boat covers a distance of 1km against the current of the stream in half an hour and a distance of 3km in the direction of the current in 30minutes. How l...
- The present average age of X, Y, and Z is 44 years. 8 years ago the average age of X and Y was 38 years. What is the present age of Z?
- Eight years ago, a man's mother was three times the age of her son. After eight years, the mother's age will be twice the age of her son. What is the ratio...
- Question 6
- A shopkeeper sells a book at a loss of 60 percent. Had he sold the book for Rs. 150 more, then he would have suffered a loss of 30 percent. To earn a profi...
- Three cans having capacity of 28 kg, 42 kg and 70 kg are completely filled with three types of rice, type A, type B and type C respectively. The three type...
- Find the LCM of 15, 24, 35 and 54.
- 56% of Y is 182. What is Y?
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt