      Question

      A can complete 40% of a work in 6 days, while 'B' can

      complete the work in 7 days. If they work together, then in how many days will the work be completed?
      A 4 Correct Answer Incorrect Answer
      B 7 Correct Answer Incorrect Answer
      C 6 Correct Answer Incorrect Answer
      D 5 Correct Answer Incorrect Answer

      Solution

      The correct answer is D

      Practice Next