Question
A can do a work in 20 days, B can do in 30 days and C
can do in 60 days. If A is helped by B and C every third day. The number of days they will take to competed the work is:Solution
ATQ, The efficiency of A is 1/20 The efficiency of B is 1/30 The efficiency of C is 1/60 1st day work by A = 1/20 2nd day work by A = 1/20 3rd day work by A + B + C = 1/20 + 1/30 + 1/60 ⇒ (3 + 2 + 1)/60 = 1/10 Work completed in 3 days ⇒ 1/20 +1/20 + 1/10 = 1/5 Time is taken to complete the work ⇒ 3 × 5 = (1/5) × 5 ⇒ 15 days = 1 ∴ In 15 days the work will be completed.
The germination of seeds while still on the mother plants is known as ____
What is the premium for Kharif crops in PMFBY?Â
What is the average crop duration for banana before harvest?
Which plant hormone is responsible for cell elongation in fruits ?
The strategy of using as many out lets as possible is called
The stickiness in rice is due to ____Â
Which process involves the removal of sodium ions from soil?
Among the following, which is not a breed of goat?
Which of the following is the latest addition to the list of essential nutrients?
The term ‘mixed farming’ refers to: